A sprint review is a time-boxed event of 4 hours for a one-month Sprint. It can be shorter for a shorter sprint.
The target of the sprint review is that all the Scrum Team present the work to the key stakeholders. In this event, you get feedback on your position and foster empiricism.
The scrum guide state that:


During the event, the Scrum Team and stakeholders review what was accomplished in the Sprint and what has changed in their environment. Based on this information, attendees collaborate on what to do next. The Product Backlog may also be adjusted to meet new opportunities. The Sprint Review is a working session and the Scrum Team should avoid limiting it to a presentation.

Scrum guide 2020- Sprint Review

For the exam remember that:

  • Sprint Review is 4 hours boxed event for a one-month sprint; it can be shorter for the shorter sprint;
  • All the scrum team and the main stakeholder attend the Sprint Review;
  • The target is to foster empiricism by inspecting the work done.